C-25-0111Completed
Fiber Optic Network Extension
Fiber extension linking five city facilities.
- Original value
- $460,000
- The amount awarded
- Published changes
- +$21,500
- 1 executed change
- Current value
- $481,500
- What it stands at now
- Change from original
- +4.7%
- Against the awarded amount
Contract Details
- Vendor
- Crestline Communications
- Department
- Information Technology
- Category
- Technology
- Award date
- October 6, 2025
- Start date
- October 26, 2025
- End date
- March 15, 2026
- Renewal options
- None
- Fiscal year
- FY 2025
- Project manager
- Lauren Diaz
- Procurement officer
- Sarah Chen
- Competition
- Competitively bid with 4 bidders
Changes to This Contract
An amendment is a formal change to the contract after it was signed. It can add money, add time, or change the work.
- Change order 1ExecutedAdds $21,500
Directional bore under rail crossing
- Reason for the change
- Rail crossing required directional boring instead of open trench.
- Approved
- December 15, 2025
Contract Documents
No public documents have been posted for this contract. Copies may be requested through a public records request.